The original bid to install Hangars at the Lakewood airport was at $2,208,638.00 (Two Million, Two Hundred Eight Thousand, Six Hundred Thirty Eight and 00/100 Dollars) Now the contractor asked for an additional 185K because "these additional charges were not included in the bid response but were caused by conditions that were outside of the control of the Contractor."
After Monmouth executive airport kicked out private plane owners they pushed a plan to store their planes at Lakewood airport. The LIC which is not an elected board( The same guys who signed the Blue Claws deal) spent 2.5 million of our tax dollars with a promise of bringing in revenue to the township by charging rent to keep these planes at the airport. The same logic was used to justify building the stadium which cost over 30 million and did not generate a penny back to the tax payers.
see the approval HERE and below.
WHEREAS, sealed bids were received on December 17, 2015 for the construction of this
project which resulted in an award of construction contract to Iorio Construction Company, 700
Vassar Avenue, Lakewood, NJ 08701 in the amount of $2,208,638.00
(Two Million, Two Hundred
Eight Thousand, Six Hundred Thirty Eight and 00/100 Dollars) for completion of all planned
aspects of this phased project for three hangar structures; and
WHEREAS, the following contract change orders were presented for the following
reasons:
All material, labor and equipment necessary to complete the following work and to adjust the total
contract as indicated:
005b JCP&L Electric Service Option 2 (site prep / clearing / installing conduits
2-5” pull boxes
$160,909.80
006 Winter Charges Hangar #1- concrete and additives 12/13/16 $3,421.44
007 Winter Charges Hangar # 2- concrete and additives 12/21/16 $3,654.00
008 Winter Buckets and Blankets $8,146.80
009R Cost for winter concrete, additives for Hangar #3 1/9/17 (request for
overtime removed)
$5,565.24
010R Cost for winter concrete, additives for Building #1, 2 & 3 (request for
overtime removed)
$631.80
T:\(LIC) ---Lkwd Industrial Comm\0- MEETING PREPARATION\RESOLUTIONS\2017 Resolutions\070401 Change Order Iorio
CO#s 005b thru 012.docx
WHEREAS, Project Manager, Kenneth Ressler (RVE) reviewed the change orders
presented by the Contractor for accuracy and made comparison to the specifications prepared and
responded to by the Contractor; and WHEREAS, the above change orders reflect that these additional charges were not included in the bid response but were caused by conditions that were outside of the control of the Contractor.
THEREFORE, BE IT RESOLVED, and based on the above justifications, the Lakewood
Industrial Commission hereby authorizes Change Order #005b, 006, 007, 008, 009R and 010R as requested.
I hereby certify the above to be a true copy of a resolution
adopted by the Industrial Commission of the Township of
Lakewood, Ocean County, New Jersey at its meeting held
on the 5th day of April, 2017.
__________________________________________
GREGORY B STAFFORD-SMITH, Secretary
or Steven Reinman, as Secretary-designee, in the
absence of the Secretary
After Monmouth executive airport kicked out private plane owners they pushed a plan to store their planes at Lakewood airport. The LIC which is not an elected board( The same guys who signed the Blue Claws deal) spent 2.5 million of our tax dollars with a promise of bringing in revenue to the township by charging rent to keep these planes at the airport. The same logic was used to justify building the stadium which cost over 30 million and did not generate a penny back to the tax payers.
see the approval HERE and below.
WHEREAS, sealed bids were received on December 17, 2015 for the construction of this
project which resulted in an award of construction contract to Iorio Construction Company, 700
Vassar Avenue, Lakewood, NJ 08701 in the amount of $2,208,638.00
(Two Million, Two Hundred
Eight Thousand, Six Hundred Thirty Eight and 00/100 Dollars) for completion of all planned
aspects of this phased project for three hangar structures; and
WHEREAS, the following contract change orders were presented for the following
reasons:
All material, labor and equipment necessary to complete the following work and to adjust the total
contract as indicated:
005b JCP&L Electric Service Option 2 (site prep / clearing / installing conduits
2-5” pull boxes
$160,909.80
006 Winter Charges Hangar #1- concrete and additives 12/13/16 $3,421.44
007 Winter Charges Hangar # 2- concrete and additives 12/21/16 $3,654.00
008 Winter Buckets and Blankets $8,146.80
009R Cost for winter concrete, additives for Hangar #3 1/9/17 (request for
overtime removed)
$5,565.24
010R Cost for winter concrete, additives for Building #1, 2 & 3 (request for
overtime removed)
$631.80
T:\(LIC) ---Lkwd Industrial Comm\0- MEETING PREPARATION\RESOLUTIONS\2017 Resolutions\070401 Change Order Iorio
CO#s 005b thru 012.docx
WHEREAS, Project Manager, Kenneth Ressler (RVE) reviewed the change orders
presented by the Contractor for accuracy and made comparison to the specifications prepared and
responded to by the Contractor; and WHEREAS, the above change orders reflect that these additional charges were not included in the bid response but were caused by conditions that were outside of the control of the Contractor.
THEREFORE, BE IT RESOLVED, and based on the above justifications, the Lakewood
Industrial Commission hereby authorizes Change Order #005b, 006, 007, 008, 009R and 010R as requested.
I hereby certify the above to be a true copy of a resolution
adopted by the Industrial Commission of the Township of
Lakewood, Ocean County, New Jersey at its meeting held
on the 5th day of April, 2017.
__________________________________________
GREGORY B STAFFORD-SMITH, Secretary
or Steven Reinman, as Secretary-designee, in the
absence of the Secretary